District Overview

Of the four school buildings, three of them have various components and systems that have exceeded their projected life-cycles.

Alloway Creek Intermediate School was completed in 2003, has been well maintained, and with continued maintenance should not provide any major issues in the foreseeable future. The Intermediate School houses the District Administration Office.

The High School was originally constructed in 1960 and has received two substantial additions since 1993. The structure continues to function as designed, however various systems and components will require attention in the foreseeable future. Upgraded/new systems and replaced components should provide more cost-effective operations and extended life.

Maple Avenue Middle School was originally constructed in 1932 with substantial additions in 1973 and 1991. The building still utilizes a number of components from the 1932 construction including some wood structure and egress components in the three story portion. The Middle School contains the District's preparation kitchen.  

Rolling Acres Elementary School was originally constructed in 1952 and received substantial additions in 1972 and 1990. All major components and systems are 20 plus years of age and should be thoroughly inspected for potential pending issues. There are significant accessibility and acoustical issues in the 1972 portion of the building, including the gymnasium that is only accessible from stair towers.

The Transportation and Maintenance Building was constructed in 2001 and is fully utilized. Several efficiency, safety and operational issues have been identified and should be considered as the opportunities are presented.

The Stadium, Concession Stand, and Toilet Facilities have served the District for many years with limited upgrades. Consequently, there are a number of accessibility and safety issues that will need to be addressed in immediate future.

LASD Property with Wet Areas and Topographical Views

LASD Overall District Aerial Map with Boundaries - Base Map

Littlestown Area School District Aerial Image (Overall Campus)

LASD Overall District Aerial Map with Boundaries - Property Lines - Wetlands

Littlestown Area School District Aerial Image (Overall Campus)


Master Plan for Athletic Facility Improvements - June 2017


Campus Improvements Presentation - February 2017


Press Release: Safe Fields Alliance and Synthetic Turf Council Response to EPA Status Report


District Campus Improvements for Athletic Facility Upgrades

Athletic Layout

Extra Curricular Update - October 2016


Athletic Projects Update June 7, 2016


Building Project Update - May 9, 2016


4th & 5th Grade Move for 2016-2017 - Q & A


Front Facade of the new Alloway Creek Elementary School

Alloway Creek ES - FrontFacade

Updated Site Plan Graphic for Alloway Creek Elementary School Play Areas - 1-18-16

Updated Site Plan

Act 34 Public Hearing Presentation


Building Project Update - January 2016


Extra-Curricular Projects - October 2015


Building Renovation Update - August 2015


Building Renovation Update - June 2015


MA Before Pictures

 


Building Projects

Calendar

Alloway Creek Elementary School

Begin/Submission

Completion Date

Overall Proposed Schedule May 2015 August 2017
PDE PlanCon A & B Review August 4, 2015  
PDE PlanCon Process (Act 34 Hearing) August 4, 2015 End 2017
Code Review/L&I Plans & Existing Info (Survey) July 2015 March 2016
Anticipated Land Development (6 to 9 months)    
Existing Building Surveys & Staff Meetings Late August 2015 March 2016
Out to Bid March/April 2015  
Start of Construction May/June 2016  
Project Substantially Complete   August 2017

Stadium/Athletic Improvements

Begin/Submission

Completion Date

Overall Proposed Schedule June 2015 August 2017
Anticipated Land Development (6 to 9 months)    
Naming Rights/Donations March 2016  
Out to Bid March 2017  
Start of Construction May 2017  
Project Substantially Complete   August 2017

High School Selective Reroofing

Begin/Submission

Completion Date

Athletic Meeting August 27, 2015  
First Advertisement to Bid August 27, 2015  
Second Advertisement to Bid August 30, 2015  
Drawings/Specifications Available August 31, 2015  
Pre-bid at Maintenance Bldg and Tour Roof at 1:30 PM September 3, 2015  
Third Advertisement to Bid September 6, 2015  
Receipt of Bids in District Office at 2:00 PM September 10, 2015  
Begin Roof Replacement Construction October 9, 2015 November 20, 2015

Littlestown Area School District Meeting Schedule

Day Day of Week Meeting Type Location/Time
April 13, 2015 Monday Board Work Session; CRA to proceed with Feasibility Study DO / 7 PM
April 15, 2015 Wednesday CRA Design Team Meeting; Review Feasibility Study and Contact Engineers CRA Only
April 20, 2015 Monday Board Voting Meeting DO / 7 PM
April 24, 2015 Friday Design Team Kick-Off Meeting; Discuss LASD Feasibility Scope, Budget and Schedule and Review To Do & Needs List CRA Office TBD
Wk of April 27, 2015 All Week Tour of District Buildings and Discuss Concerns/Needs TBD
May 1, 2015 Friday Design Team Meeting; Review Bldg Options and Scope; Review Rough Estimates; Review To Do & Needs List DO / 1-3 PM
May 8, 2015 Friday Design Team Meeting; Refine Bldg Options, Review Preliminary Estimates, Review To Do and Needs List CRA / 1-3 PM
May 11, 2015 Monday Board Work Session; Update/Status DO / 7 PM
May 14, 2015 Thursday Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List TBD / 1-3 PM
May 18, 2015 Monday Board Voting Meeting DO / 7 PM
May 21, 2015 Thursday Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List TBD / 1-3 PM
May 28, 2015 Thursday Design Team Meeting; Review Feasibility Study Progress, review To Do and Needs List TBD / 1-3 PM
June 1, 2015 Monday Board Work Session; Discuss Project Options and Ideas DO / 6:30 PM
June 2, 2015 Tuesday Voluntary Employee Meeting to Provide Input and Receive Updates for Building and Extra-Curricular Renovations MA Aud / 3:45
June 4, 2015 Thursday Design Team Meeting; Review Feasibility Study Progress, Review To Do and Needs List TBD / 1-3 PM
June 8, 2015 Monday Town Hall Meeting; Provide Input and Receive Updates for Building and Extra-Curricular renovations MA Aud. 6 PM
June 11, 2015 Thursday Design Team Meeting/ Review Feasibility Study Progress, Review To Do and Needs List TBD / 1-3 PM
June 15, 2015 Monday Board Work Session; Update review draft of amended Feasibility Study DO / 6 PM
June 16, 2015 Tuesday Voluntary Employee Meeting to provide input and receive updates for building and extra-curricular renovations RA Cafe/4 PM
June 17, 2015 Wednesday Town Hall Meeting; Provide input and receive updates for building and extra-curricular renovations MA Aud  6 PM
June 18, 2015 Thursday Design Team Meeting; Final Review of Feasibility Study CRA / 1-3 PM
June 22, 2015 Monday Board Voting Meeting; Approve amended Feasibility Study DO / 7 PM